Project Roadmap
OctoLLM development follows a 7-phase roadmap from architecture to production deployment.
Overall Timeline
Estimated Total Time: 36-48 weeks (8-11 months) Estimated Total Hours: ~1,186 development hours Current Progress: ~22% (Phase 0 complete, Phase 1 40%)
Phase Overview
| Phase | Status | Duration | Team | Est. Hours |
|---|---|---|---|---|
| Phase 0: Project Setup | ✅ 100% | 1-2 weeks | 2-3 eng | ~80h |
| Phase 1: Proof of Concept | 🚧 40% | 4-6 weeks | 3-4 eng | ~200h |
| Phase 2: Core Capabilities | ⏳ 0% | 8-10 weeks | 4-5 eng | 190h |
| Phase 3: Operations | ⏳ 0% | 4-6 weeks | 2-3 SRE | 145h |
| Phase 4: Engineering | ⏳ 0% | 3-4 weeks | 2-3 eng | 90h |
| Phase 5: Security | ⏳ 0% | 8-10 weeks | 3-4 eng | 210h |
| Phase 6: Production | ⏳ 0% | 8-10 weeks | 4-5 eng | 271h |
Phase 0: Project Setup
Status: ✅ COMPLETE (100%) Duration: 2025-11-10 to 2025-11-13
Deliverables
- ✅ Repository structure and Git workflow
- ✅ CI/CD pipeline (GitHub Actions)
- ✅ Complete documentation (170+ files)
- ✅ Architecture specifications
- ✅ OpenAPI specs for all services
- ✅ Security audit framework
Phase 1: Proof of Concept
Status: 🚧 IN PROGRESS (40%) Start: 2025-11-14
Completed
- ✅ Sprint 1.1: Reflex Layer (v1.1.0)
- ✅ Sprint 1.2: Orchestrator Core (v1.2.0)
Remaining
- 🚧 Sprint 1.3: Planner Arm (PLANNED)
- ⏳ Sprint 1.4: Tool Executor Arm
- ⏳ Sprint 1.5: Integration Testing
Phase 2: Core Capabilities
Status: ⏳ NOT STARTED Dependencies: Phase 1 complete
Goals
- All 6 arms operational (Planner, Executor, Retriever, Coder, Judge, Safety Guardian)
- Distributed memory system
- Swarm decision-making
- Advanced error handling
Phase 3: Operations & Deployment
Status: ⏳ NOT STARTED Dependencies: Phase 2 complete
Goals
- Kubernetes deployment
- Monitoring stack (Prometheus, Grafana, Loki, Jaeger)
- Scaling and performance tuning
- Operational runbooks
Phase 4: Engineering & Standards
Status: ⏳ NOT STARTED Dependencies: Phase 3 complete
Goals
- Code review processes
- Engineering standards
- Performance optimization
- Technical debt management
Phase 5: Security Hardening
Status: ⏳ NOT STARTED Dependencies: Phase 4 complete
Goals
- Comprehensive security testing
- Penetration testing
- Compliance certifications (SOC 2, ISO 27001)
- Vulnerability management
Phase 6: Production Readiness
Status: ⏳ NOT STARTED Dependencies: Phase 5 complete
Goals
- Production deployment
- Public API
- Documentation for external users
- SLA and support setup
Critical Milestones
- Week 3 (✅ DONE): Development environment ready, first code commit
- Week 10: POC complete, basic orchestrator + 2 arms functional
- Week 20: All 6 arms operational, distributed memory working
- Week 26: Kubernetes deployment, monitoring stack operational
- Week 34: Security hardening complete, penetration tests passed
- Week 42: Production-ready, compliance certifications in progress